How many days do you have to file a preliminary notice with the Construction Registry after commencing work?

  1. 10

  2. 20

  3. 30

  4. 60

The correct answer is: 20

Filing a preliminary notice is an important step in the construction process, particularly in the context of securing lien rights and ensuring proper communication with all parties involved. In Utah, contractors are required to file this notice within a specific timeframe to protect their legal interests. The correct timeframe for submitting a preliminary notice after commencing work is indeed 20 days. Filing within this period is vital as it notifies property owners, general contractors, and subcontractors of your involvement in the project. This proactive step helps in establishing a clear record of your rights to payment and can be crucial if disputes over payment arise later on. While 10, 30, and 60 days may seem reasonable for notice periods in different contexts, they do not align with the regulations governing preliminary notices in Utah. Adhering to the 20-day requirement ensures compliance with state laws and facilitates smoother transaction flows in the construction arena.